Racks G126% et G127%
Scheduled Maintenance Report for Network & Infrastructure
Completed
Summary : We are planning to connect a new Cooling System for the G126% and G127% racks. Monday june 19th, we will activate the new cooling system in parallel of actual system and we will make frequent checks to validate the cooling system sustainability. Tuesday june 20th, we will disable the initial cooling system and continue to make frequent checks.
Actions: Replace the cooling system.
Start : We scheduled on monday june 19th at 10h00 (UTC +1)
Affected Rack : G126% G127%
Impact : None, the cooling system is redundant.
Estimated Time : 2 days

Update(s):

Date: 2017-06-26 14:25:35 UTC
Intervention is done

Date: 2017-06-26 08:06:00 UTC
Intervention is started

Date: 2017-06-21 12:49:00 UTC
We need to intervene on a defective part of cooling system.
We start new intervention this Monday 26 june 2017 at 10.00AM
No impact, the cooling system is redundant.
Posted Jun 13, 2017 - 12:08 UTC