OVHcloud Network Status

Current status
Legend
  • Operational
  • Degraded performance
  • Partial Outage
  • Major Outage
  • Under maintenance
FS#4711 — Preventive maintenances of the UPS
Scheduled Maintenance Report for Network & Infrastructure
Completed
We will perform a series of preventive maintenances of the UPS.
The uninterruptible power supply will be by-passed during the manipulations.

We will start today with UPS 3 at RBX 2.

Update(s):

Date: 2010-11-25 09:34:56 UTC
The preventive maintenance will take place on UPS 1 RBX 3 today (room 41).
The UPS will be by-passed during the operations.

Date: 2010-11-17 12:22:55 UTC
We will do the maintenance on UPS 5 of RBX 2.

Date: 2010-11-08 19:04:25 UTC
The batteries on UPS4 were replaced.
Remains the maintenance to perform on UPS 6 and 7.



Date: 2010-10-22 12:52:11 UTC
The manufacturer has received the replacement batteries.
The technicians are currently intervening.

Date: 2010-10-20 19:16:15 UTC
UPS 3 was maintained Tuesday.

UPS 4 was updated on Wednesday. During the intervention, we had a
problem on two batteries. The battery branch has been isolated the time
to be able to replace defective batteries.
Posted Oct 19, 2010 - 08:09 UTC